Bridge Design
GM2 Associates, Inc. provides a wealth of bridge design expertise, from
simple span local bridges to major hybrid curved steel viaducts to timber
design. Collectively, GM2 has seven full-time bridge engineers on staff,
and all are licensed professional engineers. GM2's bridge design
engineers have completed more than 1000 bridges over the spans of their
careers, which highlights the in-depth technical and proven ability of
this team.
Recent Bridge Engineering Experience:
- 21 Local Town Road Bridges over waterways, CT
- 3 Local Town Road Bridges
over waterways, MA
- List 9 Bridges – (Rte 1, Rte 12, Rte 163), CT
- List 13 Bridge – MNRR over Rowayton Avenue, CT
- List 14 Bridge – I-84
in Tolland, CT
- List 14 Bridge – Howard Ave. over I-95, New Haven, CT
- List
14 Bridge – Rte 15 over the Mill River, Fairfield, CT
- List 15-18 Bridges – Rte
58 (2), Rte 37, Rte 110, CT
- I-95 and Ramp S-1 over Fulton Terrace, New
Haven, CT
- Island Pond over I-293 and 93, Manchester, NH
Recent Examples of Work Include:
Route 7/15 Interchange, Structure No.
1 – Norwalk, CT
A 57 m, two-span continuous welded plate girder system.
The project is under construction. Estimated construction cost of the bridge
is $2,750,000.
I-95 over Route 1 West, Bridge No. 00134 – Stratford,
CT
A 158-foot, single-span welded steel plate girder system with full-height
cantilever-type reinforced concrete abutments and wingwalls. The project
is designed for a three-stage construction. The design is 100% complete.
Estimated construction cost is $5,300,000.
Burritt Street over I-84 – Southington,
CT
A 73 m, two-span structure with 1800 mm deep New England Bulb
Tees and a reinforced concrete deck made continuous for live loads. The
substructure included full-height reinforced concrete abutments and bent-type
center pier. The project was designed for two-stage construction. The bridge
construction is complete. The construction cost was $3,400,000.
Route 2 West Viaduct
over I-84 – East Hartford, CT
A 1,600-foot ramp structure
consisting of 10 spans with curved and straight segments. The superstructure
consists of twin box girders and a reinforced concrete deck. Piers are
single circular concrete columns with cantilever cap. Construction is complete.
Final cost of the bridge was $11,300,000. Personal experience of Madan
Gupta, designed for Parsons Brinckerhoff. Click
here for photos.
Route I-91 N.B. over Route 15 – Hartford,
CT
A 430-foot, two-span continuous structure with welded plate
girders. The bridge has a 65 degree skew. The substructure consists of
full-height reinforced concrete abutments and round concrete columns supported
on individual footings. Construction is complete. Final cost of the bridge
was $6,600,000.
Route 7 over I-95 – Norwalk, CT
Deck and wearing surface
replacement and rehabilitation of superstructure steel girders and concrete
substructure on a 336-foot, two-span continuous bridge. Construction is
complete. Construction cost was $3,750,000.
Route 1 over Mennunketesuck River – Westbrook, CT
An
82-foot, simple-span bridge with prestressed concrete box beams. Construction
was completed in 2003. This was an assignment from ConnDOT under the Bridge
Rehabilitation Program, List 9. Construction cost of the project was $3,300,000.
Metro-North Railroad over Rowayton Avenue – Norwalk, CT
A
55-foot span bridge with concrete-encased welded steel plate girders fabricated
in 3-foot wide
sections. The bridge is supported on drilled concrete filled steel piles.
Project is designed for a four-stage construction to replace one track
at a time. The project is presently under construction with an estimated
bridge cost of $3,800,000.
Island Pond Road Bridge over I-93 & I-293 – Manchester,
NH
Two 136-foot single span bridges. The superstructure consists of
steel plate girders of 50 ksi yield strength composite with a reinforced
concrete deck on prestressed precast concrete deck panels. The substructure
consists of full height abutments and wingwalls. The project is under design.
Anticipated construction is two years. Estimated construction cost is $7,000,000.
The Pearl Harbor
Memorial Bridge – New Haven, CT
This project involved building
3-D finite element models for multi-modal analysis of multi-span bridges,
nonlinear push-over analysis, and plastic hinge detailing. The viaduct
consists of eleven proposed bridges, and a temporary crossover bridge that
is used during staged construction of the viaduct. The substructures include
multi-column reinforced concrete bents and straddle bents supported on
precast pile foundations, and multi-column bents on drilled shafts. Certain
span lengths of the cap beams are up to 40 meters between columns. The
seismic results were used to design the cross-frames of the curved superstructure,
bearings, piers, and the foundations. The foundations were designed using
the seismic forces and soil structure-interaction stiffness calculated
from a non-linear finite element program. The seismic models were also
modified to determine the thermal movements. The FEM computer codes that
the firm uses for such work are GT Strudl, STAAD, and LARSA 2000. Additionally,
a flood plain analysis for the proposed new Q-Bridge structure was performed
using the program HEC-RAS. In conjunction
with this effort, GM2 was responsible for the demolition sequence of the
entire existing structure and the design of two single-span bridges over
Fulton Terrace. Both bridges utilize steel plate girders and are part of
contract B of the corridor improvements. Click
here for photos.
Old Forge Road Bridge – Colebrook, CT
Honorable Mention at the Connecticut Engineers in Private Practice
1997 Awards Ceremony. Prestresed box beams, precast architectural arch, granite
curbing, and cap stones. 85-foot span over trout-stocked Sandy Brook in
a pristine country setting. Dangerous Y-intersection and steep grades were
replaced with a T-intersection and gentle grade. 600-foot roadway reconstruction. Click
here for photos.
Fabyan-Woodstock Road Bridge – Thompson, CT
Project involved curved 80-foot prestressed concrete deck units,
one new abutment at the west approach, and widening of the existing east
abutment, plus total horizontal and vertical realignment of approaches. Click
here for photos.
McClave Hill Road – Colebrook, CT
Bridge features a recast, reinforced concrete rigid frame with new
Cast-In-Place reinforced concrete wingwalls. McClave Hill Road provides access
to the popular YMCA "Camp
Jewell." A new
sidewalk for fishing access was included. The GM2 design minimized impact
to the waterway and the Inspection team closely monitored compliance to all
permits. The bridge was opened in the Spring of 2001, on schedule and budget. Click
here for photos.
Beech Hill Road – Colebrook, CT
42-foot prestressed concrete deck units, one new RCC abutment
at the west approach, widening of existing east abutment, and total horizontal
and vertical realignment of approaches. GM2 was responsible for the initial
bridge safety inspection, application process, design, and construction inspection
of this bridge. Click
here for photos.
Stone Mill Road Bridge – Mansfield, CT
GM2 is designing a replacement structure for the existing two-span
Stone Mill Bridge. The bridge site, located approximately 35 feet from the
historic Grist Mill Building, makes aesthetics an important consideration
for the new bridge. Pending final approval from the town, the replacement
structure will consist of a two-span concrete arch with a stone masonry facing
to compliment the historic surroundings. Click
here for photos.